Various Lane Closures on SR 400 and Pilgrim Mill Road Expected August 17-20
SR 400 will have various scheduled north and southbound daytime lane closures and traffic paces at Pilgrim Mill Road for bridge construction Monday, Aug. 17, through Wednesday, Aug. 19. Commuters can also expect a nighttime single lane closure on Pilgrim Mill Road (westbound) at SR 400 on Wednesday, Aug. 19, and Thursday, Aug. 20.
Below is the schedule of planned traffic impacts:
Monday, Aug. 17 (7 a.m. to 3 p.m.)
• Single lane (inside) closure on SR 400 northbound at Pilgrim Mill Road
• Several traffic paces on SR 400 northbound
Monday, Aug. 17 (9 a.m. to 5 p.m.)
• Single lane (outside) on SR 400 southbound at Pilgrim Mill Road
• Several traffic paces on SR 400 southbound
Tuesday, Aug. 18, (7 a.m. to 3 p.m.)
• Single lane (inside) closure on SR 400 northbound at Pilgrim Mill Road
• Several traffic paces on SR 400 northbound
Wednesday, Aug. 19 (9 a.m. to 5 p.m.)
• Single lane (outside) closure on SR 400 southbound at Pilgrim Mill Road
• Several traffic paces on SR 400 southbound
Wednesday, Aug. 19 (7 p.m. to 5 a.m.)
• Single lane closure on Pilgrim Mill Road westbound at SR 400
• Multiple traffic paces on SR 400 northbound
Thursday, Aug. 20 (7 p.m. to 5 a.m.)
• Single lane closure on Pilgrim Mill Road westbound at SR 400
• Multiple traffic paces on SR 400 southbound
The work is weather dependent which could result in some fluctuation. Updates will be posted on the County Facebook and Twitter pages as necessary.